Decision Maker: Investment Committee
Decision status: Recommendations approved
Is Key decision?: No
Is subject to call in?: No
To approve the Climate Programme Bidding Round
Outline Business Case and funding to progress to Full Business Case
stage
RESOLVED:
A. To make recommendations to the CPCA Board for the approval of the Full Business Case for the Peterborough Station Quarter, including and funding of £47.85m capital investment from HM Government’s Levelling Up Fund which has been included in the MTFP, subject to approval from the Department for Transport
B. To make recommendations to the CPCA Board for the approval of the Change Request and increased funding of £2m to deliver the Cygnet Bridge project
C. To approve the Change Request for a timing change for the Waterbeach Renewable Energy Network (WREN) project.
Report author: Nathan Bunting
Publication date: 14/01/2025
Date of decision: 13/01/2025
Decided at meeting: 13/01/2025 - Investment Committee